Groundwater Bottling Facility in Middleway

What is happening

The red line above shows the path the trucks will take to the plant. The blue line above shows the path of the pipeline.

Background (click to expand)

The industrial facility in Middleway, known locally as the 3M plant, was run by Eastman Kodak until 2006. The property was remediated through the voluntary remediation program between 2014 and 2019. The groundwater is contaminated with two industrial pollutants (Trichloroethane and cis-2,3 Dichloroethene) and the property contains two closed industrial landfills, contaminated spill ponds, and contaminated soil. In 2020 for a period of time the property was used as a hemp growing facility. Sidewinder Enterprises (which owns the highlighted properties in the above image) has since acquired this facility and several small properties containing part of Turkey Run upstream of Middleway and Lake Louise (a karst water feature that is small in surface area but thought to be very deep in the middle).

More information

In the Jefferson County Zoning and Land Development Ordinance there are three categories of land uses in each zone:

Principal Permitted Uses – Uses with this designation in a zone are allowed by right in that zone. They are still subject to the requirements in the concept plan and the site plan process but the use is allowed by right.

Conditionally Permitted Use – Uses with this designation in a zone are only allowed if they obtain a conditional use permit from the Board of Zoning Appeals. The board of zoning appeals may reject or place requirements or restriction on a conditional use permit.

Prohibited Use – Uses with this designation in a zone are not allowed in that zone.
 
When a concept plan is submitted to the Planning Commission (the first step in the development process) the staff and the planning commission members must determine if the land use is permitted in the zone where the subject property is located. If the use is a Principal Permitted Use the application may continue to the concept plan process. If the land use requires a conditional use permit the concept plan must be rejected and the developers must proceed to the Board of Zoning Appeals to apply for a conditional use permit. If the land use is a prohibited use the concept plan should be rejected.

How is CTUB Involved

CTUB (Charles Town Utility Board) entered into an agreement with Sidewinder in April of 2024. Unfortunately, this agreement was not considered in a robust public process. In fact, according to the CTUB general manager there are no meeting agendas or meeting minutes that reflect an agenda item, discussion, or action on such an agreement. We are frustrated that CTUB has clearly not been following the Open Meetings Act, which requires that all items to be discussed or acted on be listed on the agenda with enough specificity that the public can determine the topic to be discussed.

The agreement itself however provides protection to the public of Middleway and Jefferson County by placing some of the infrastructure in control of CTUB. CTUB is a public utility so it is bound by the Open Meetings Act and the Freedom of Information Act. These laws and an appointed board provide transparency and accountability to the people. This will give us in site to the project that we would not have had without the agreement.

Agreement Highlights

The Developer will design the project.
CTUB will evaluate the design of the project before construction.
The Developer will obtain and pay for all approvals.
The Developer will construct and pay for the construction of the infrastructure.
CTUB will aid in obtaining easements.
CTUB will inspect the constructed infrastructure.
The Developer will do the testing and preparation of the infrastructure.
Developer will provide the plans and CTUB may inspect them.
During construction the Developer will own the infrastructure.
The Developer will have the infrastructure certified and approved.
The Developer will notify CTUB of completion.
CTUB has 45 days to inspect and require repairs if needed.
The developer shall deliver and CTUB shall accept ownership of the project.
The developer shall lease the land the water treatment plant it is on to CTUB (100 yrs. $1).
The developer will maintain and operate the wells.
CTUB will maintain and operate the water main and the treatment plant.
CTUB has first right of refusal for purchase of the wells and the land parcels.
If the developer sells the buyer will maintain the agreement.

Update on the legal case